EVANSTON INSURANCE COMPANY, et al v. WESTCHESTER SURPLUS LINES INSU, et al

ATTENTION: It is possible that this information may no longer be current and therefore may be inaccurate. The index contains both open and closed cases and is not a complete list of cases in which an ACE Insurance Group company is involved. This information is provided to give interested persons an idea of the issues disputed in the indexed cases. For a full understanding of a case, one should read the rest of the court file, including the response. For the most up-to-date and complete information on a case, visit www.pacer.gov or contact the clerk of the relevant court.

Case Number: 
2:07-cv-00923-MJP Search Pacer
Opposing Party: 
2:07-cv-00923-MJP
Court Type: 
Federal
US District Court: 
United States. Court of Appeals (9th Circuit)
Date Filed: 
Jun 14 2007

"American Guarantee & Liability Insurance Company (“American Guarantee”) appeals from the district court’s judgment, following a bench trial, in favor of Westchester Surplus Lines Insurance Company (“Westchester”) and Royal Insurance Company (“Royal”), in this “additional insured” insurance coverage dispute.1 The district court concluded that Northwest Tower Crane Services (“Northwest”), a subcontractor at a large construction site, did not enter into a contract requiring Northwest to add Bellevue Master LLC (“Bellevue Master”) as an additional insured on Northwest’s liability insurance policies.2 We have jurisdiction pursuant to 28 U.S.C. § 1291. We reverse.

“We review the district court’s findings of fact after a bench trial for clear error and review the district court’s conclusions of law de novo.” Bertelsen v. Harris, 537 F.3d 1047, 1056 (9th Cir. 2008). The interpretation of an insurance contract is a question of law that is reviewed de novo. Holden v. Farmers Ins. Co. of Wash., 239 P.3d 344, 347 (Wash. 2010) (citations omitted). The district court erred when it concluded that Northwest did not agree in a contract to make Bellevue Master an additional insured. “A unilateral contract exists when one party offers to do a certain thing in exchange for the other’s performance, and performance by the other party constitutes acceptance.” Cascade Auto Glass, Inc. v. Progressive Cas. Ins. Co., 145 P.3d 1253, 1258 (Wash. Ct. App. 2006) (citing Knight v. Seattle First Nat’l Bank, 589 P.2d 1279 (Wash. 1979)). The fax from Bellevue Master to Northwest on February 22, 2001 was an offer: Northwest would be able to continue working as a subcontractor at the construction project provided it complied with Bellevue Master’s insurance requirements. When it contacted its insurance broker and requested that the broker issue the insurance certificate to Bellevue Master, Northwest accepted the unilateral contract.

The contract for insurance between Northwest and Bellevue Master was fully executed prior to loss, as was required for Bellevue Master to be covered under the Westchester and Royal policies. This is the case regardless of whether we look to the legal definition or to the plain and ordinary meaning of the term “executed.” Black’s Law Dictionary provides two meanings for “executed”: a written and signed contract, or a contract that has been fully performed by both parties. (9th ed. 2009). Under Washington law, undefined contractual terms must be given their “plain, ordinary, and popular” meaning. Boeing Co. v. Aetna Cas. and Sur. Co., 784 P.2d 507, 511 (Wash. 1990) (citing Farmers Ins. Co. v. Miller, 549 P.2d 9 (Wash. 1976) and Prudential Property & Cas. Ins. Co. v. Lawrence, 724 P.2d 418 (Wash. Ct. App. 1986)). The ordinary meaning of terms should be determined by looking to standard English dictionaries. Id. The Oxford English Dictionary defines “executed” as “carried out, performed, practised, inflicted.” (2d ed. 1989). Bellevue Master made an offer which Northwest accepted through performance. The contract was executed.

The additional insured coverage of the Westchester policy applies only to liability arising out of Northwest’s “ongoing operations” performed for Bellevue Master. Washington courts have interpreted such clauses and have found that “the endorsement evinces an intent to provide coverage to the additional insured only for liability that arises while the work is still in progress,” such as in the “course of construction work site accident involving bodily injury or property damage.” Hartford Ins. Co. v. Ohio Cas. Ins. Co., 189 P.3d 195, 201–02 (Wash. Ct. App. 2008). The manlift work at issue occurred in the course of Northwest’s work at the same construction project involved in Northwest’s and Bellevue Master’s earlier contracted work: the Lincoln Square Project. Thus, the work was covered by the “ongoing operations” clause.

Appellees argue that Northwest, when it performed the work at issue in this case, was working pursuant to a contract with another Bellevue Master subcontractor, so any additional insured coverage for Bellevue Master does not apply. We reject this argument. Bellevue Master contacted Northwest directly to perform the work at issue. Northwest accepted the offer, performed the work, and was paid directly by Northwest. Each party to bear its own costs on appeal."

The provided text is an excerpt from a document filed in this case. For a full understanding of the case, one should read the complete court file, including the response.